Myself and my fiancé retained Miller Building Group in August of 2021 to redo our townhouse
miller building group asked for deposits of the major items in the very early stages of the project
miller building group purposely stalled the project to avoid reaching the milestones in which the major lead items would require delivery
We are now into the 15th month and there is no sign of completion.
As of today, Miller Building Group currently holds the following deposits
-Stair stringers (6) $23,000
-36 stair treads $8,950
-kitchen cabinetry $22,175
-Built-in closets for bedrooms (3) $11,836
-Front entry closet $3,400
-Garage door $3900
-Front cement slab $5,000
-Front deck deposit $4,000
-Backyard paid in full and not complete
-Plumbing (paid in full)
-Electrical (paid in full)
-HVAC (paid in full)
Miller building group has removed all his tools from the property.
Miller building group has finally admitted to me that the funds above have been diverted.
Miller building group has left me in financial despair.
I think its very important to publicize this situation as I have no doubt that Miller Building Group is about to pray on another unsuspecting victim.
- Approximate cost of services:
- $82,000.00